Tagged: PMI-SP Dumps Questions

PMI-SP Exam Dumps | You are the project manager… 0

Questions: 41

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

A. Project calendar
B. Resource calendar
C. Organizational calendar
D. Company calendar

Answer: A

PMI-SP Practice Test | You have a project to… 0

Questions: 40

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they’ll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

A. Increase the working hours.
B. Level the project schedule.
C. Add more workers.
D. Reduce the project scope.

Answer: C

PMI-SP Exam Dumps | You are the project manager… 0

Questions: 39

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project’s cost performance index (CPI) is. What value do you report?

A. -$135,000
B. .67
C. .81
D. -$65,000

Answer: C

PMI-SP Braindumps | Tom works as the project… 0

Questions: 38

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

A. Work performance measurement
B. Stakeholder expectation management
C. Project communication management
D. Stakeholder analysis

Answer: C

PMI-SP Practice Test | Your project is installing 8,000… 0


Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

A. Risk response
B. Team development
C. Risk mitigation
D. Corrective action

Answer: D