PMI-SP Practice Test | Your project is installing 8,000… 0

QUESTION: 36

Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

A. Risk response
B. Team development
C. Risk mitigation
D. Corrective action

Answer: D

PMI-SP Questions Answer | Gary is the project manager… 0

Question: 35

Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?

A. Code of accounts
B. Chart of accounts
C. Component numbering
D. Activity linkage sequencing

Answer: A

PMI-SP Braindumps | You work as a Project Manager for Dreams… 0

Question: 34

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues
BCWP (or EV)325
BCWS (or PV) 300
ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

A. 0.923
B. 1.083
C. 1.261
D. 0.792

Answer: D