Question: 3

Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?

A. The events should be entered into qualitative risk analysis.
B. The events should be determined if they need to be accepted or responded to.
C. The events should be entered into the risk register.
D. The events should continue on with quantitative risk analysis.

Answer: C

PMI-RMP Exam Dumps | Lisa is the project manager of the SQL… 0

Question: 2

Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?

A. The level of detail is set by historical information.
B. The level of detail should correspond with the priority ranking.
C. The level of detail must define exactly the risk response for each identified risk.
D. The level of detail is set of project risk governance.

Answer: B