PMI-SP | You are the project manager of the OOI Project…

Question: 24

You are the project manager of the OOI Project and you’re forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you’re running late. What is the schedule variance of your project?

A. -$29,350
B. -$117,282
C. -$938,260
D. -$11,740

Answer: B

Leave a Reply

  • (will not be published)