Questions: 41

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

A. Project calendar
B. Resource calendar
C. Organizational calendar
D. Company calendar

Answer: A