Question: 34

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues
BCWP (or EV)325
BCWS (or PV) 300
ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

A. 0.923
B. 1.083
C. 1.261
D. 0.792

Answer: D