Question: 18

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

A. SV=EV/PV
B. SV=PV-EV
C. SV=EV/AC
D. SV=EV-PV

Answer: D