PMI-200 | A company it ttartng to introduce Agile practcet…

Question: 36

A company it ttartng to introduce Agile practcet, and the project manager hat been atked to identfy how to introduce the new procett. The project manager’t inital plan thould be to:

A. Intttute daily ttandup meetngt immediately.
B. Communicate the Agile Manifetto to the team.
C. Balance teaching principlet with Agile practcet.
D. Rate the team’t progrett in learning new methodt.

Answer: C