Question: 37

All of the statements regarding control accounts and planning packages are true EXCEPT:

A. Control accounts and planning packages are tools / techniques of Schedule Development process.
B. A control account is an assigned WBS level used to monitor cost and schedule performance of significant element of work.
C. Planning packages reflect a future segment of work within a control account that has not yet been decomposed into detailed work packages.
D. As work becomes more clearly defined, planning packages are converted into work packages.

Answer: A

  • PMI-001 dumps
  • PMI-001 dumps questions
  • PMI-001 exam dumps
  • PMI-001 exam questions
  • PMI-001 questions answers
  • PMI-001 test questions
  • Leave a Reply Cancel reply

    Your email address will not be published. Required fields are marked *

    Categories

    • Free CAPM Questions Answers
    • Free PMI-ACP Certification
    • PgMP Question Answers
    • PMI News
    • PMI-100 Questions Answers
    • PMI-200 Practice Test
    • PMI-RMP Exam Dumps
    • PMI-SP Dumps
    • PMP Dumps
    • Uncategorized

    Recent Posts

    • PMI-RMP Exam Dumps | Which one of the
    • PMI-RMP Exam Dumps | The Project Risk Management knowledge area
    • PMI-RMP Practice Test | Beth is the project manager of the BFG…
    • PMI-SP Exam Dumps | Management is concerned about your…
    • PMI-RMP Braindumps | There are five outputs of…
    • PgMP Answer Questions | Two project managers in your…
    • PMI-100 Exam Dumps | Which of the following is…
    • PMI-SP Exam Dumps | You are the project manager…
    • PMI-RMP Braindumps | John works as a project…
    • CAPM Practice Test Questions | A weighting system is…
    © 2019 PMI Exam | WordPress Theme by Superb WordPress Themes