Know how about PMI’s Certification

PMI (Project Management Institute) credentials are the most important industry-recognized certifications for IT professionals in the field of project management. Globally recognized and demanded, the PMI’s certifications demonstrate that you have the experience, education, and competency to lead and direct projects.

There are five different certifications offered by the PMI which are as follows:

1. PgMP: Program Management Professional
2. PMP: Project Management Professional
3. CAPM: Certified Associate Project Manager
4. PMI-SP: PMI Scheduling Professional
5. PMI-RMP: PMI Risk Management Professional

PMP certification is the most popular one among the five certifications offered by PMI. This is regarded as one of the most coveted and prestigious project management certifications in the world. Although it’s a difficult exam and costs are on the higher side, but there are many professional advantages of doing PMP and there is no doubt about that PMP can excel your career to new heights.

Benefits of achieving PMI's Certification

A PMI’s credential opens up great opportunities for IT professionals, on the career front. It expands your market scope and value, improves your project management skills, exhibits your ability to handle challenging projects, brings in critical projects for you, and increases your salary tremendously.

Here are the top 10 benefits of achieving this valuable Credential:

1. It is globally recognized and accepted credential.
2. It sets you apart from your non-credential peers.
3. Recognizes your project management skills worldwide.
4. Enhances your project management skills.
5. Empowers you with skills to Improve project performance.
6. Validates and displays your skills and experience in successfully completing challenging and critical industry-based projects.
7. Increases your value as a PMP and gives you the scope to lead, direct, and implement challenging projects.
8. Provides you greater job opportunities in the global project management scenario.
9. Attaining PMI credential expands your market reach by getting out to potential employers from across the globe.
10. Increases your salary noticeably.

Earn a PMI credential now and step ahead in your Project Management Career

I hope the above-given facts and information helps you to understand the benefits of passing PMI’s certification exam!! If you are looking for this valuable credential then, you should go for it as it can literally change your life. Earning a PMI’s certification confidently, you must be convinced and confident about the Excellency of your study resource and material.

PMIexam.net is giving you a full confidence and encourages your step toward a PMI certification by facilitating you with best study material. Our braindumps are most up-to-date and proven by qualified experts. They are available in PDF file format and Online Exam Engine format also. PDF dumps have a wide range of exam questions to cover the whole course contents of certification exam. Your brilliant success is 100% guaranteed by preparing these exam dumps.

PMI-ACP | The key elements of a user story in Agile… 0

Question: 45

The key elements of a user story in Agile development are:

A. a written description, the story points estimate, and the planned release.
B. conversations about the story, a written description, and success criteria about the story.
C. the story points estimate, conversations about the story, and an agreed priority.
D. tests to determine when the story is done, a written description, and the planned release.

Answer: B

PMI-SP | You will need seven other inputs to this process… 0

Question: 27

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

A. Resource calendars
B. Schedule data
C. Activity list
D. Project scope statement

Answer: B

Explanation:

Schedule data is an output of the Develop Schedule process. The nine inputs to the Develop Schedule process are: activity list, activity attributes, project schedule network diagrams, activity resource requirements, resource calendars, activity duration estimates, project scope statement, enterprise environmental factors, and organizational process assets. Answer options C, A, and D are incorrect. These are the inputs to the Develop Schedule process.

PMI-ACP | Agile communication is effective because… 0

Question: 44

Agile communication is effective because:

A. release and iteration planning keep team members aligned, daily synchronization eliminates confusion, and iteration demonstrations keep the team focused on deliverables.
B. Agile communication methods focus on detailed, written requirements and specifications that are more complete and allow the team to manage change more effectively.
C. the use of charts and diagrams over written reports creates clear, targeted communication, and customer involvement in monthly reviews eliminates changes in requirements.
D. daily iteration planning allows change to be managed, and weekly standup meetings ensure that impediments are quickly identified and effectively managed or removed.

Answer: A

PMI-SP | Samuel works as a project manager in Bluewell… 0

Question: 26

Samuel works as a project manager in Bluewell Inc. He is performing constructibility analysis in one of the initial planning phases. Which of these does constructibility take into account during analysis? Each correct answer represents a complete solution. Choose three.

A. Quality inspections and compliance
B. Location, logistics, and resource availability analysis
C. Labor productivity studies from previous similar projects in the area
D. The average price of general labor in the area

Answer: B,C,D

Explanation:

Constructibility analysis takes into account the location, logistics, resource availability analysis, the average price of general labor in the area, and labor productivity studies from previous similar projects in the area. Constructibility analysis is a process that starts in the initial planning phases and persists all over the entire planning cycle and into the implementation phase of the project. Constructibility analysis during the planning process examines the methods and cost of installed equipment and materials, technology, site conditions, resources, and related infrastructure. The benefit of constructibility analysis is to reduce both the time and cost of a project. Constructibility analysis is repeatedly performed throughout the life-cycle of a project in order to optimize cost, plan, and schedule while mitigating risk. It is a very important process that needs to be performed early in planning to allow alternatives to be considered and integrated into the design.

Answer option:

A is incorrect. This comes under the quality assurance phase.