Know how about PMI’s Certification

PMI (Project Management Institute) credentials are the most important industry-recognized certifications for IT professionals in the field of project management. Globally recognized and demanded, the PMI’s certifications demonstrate that you have the experience, education, and competency to lead and direct projects.

There are five different certifications offered by the PMI which are as follows:

1. PgMP: Program Management Professional
2. PMP: Project Management Professional
3. CAPM: Certified Associate Project Manager
4. PMI-SP: PMI Scheduling Professional
5. PMI-RMP: PMI Risk Management Professional

PMP certification is the most popular one among the five certifications offered by PMI. This is regarded as one of the most coveted and prestigious project management certifications in the world. Although it’s a difficult exam and costs are on the higher side, but there are many professional advantages of doing PMP and there is no doubt about that PMP can excel your career to new heights.

Benefits of achieving PMI's Certification

A PMI’s credential opens up great opportunities for IT professionals, on the career front. It expands your market scope and value, improves your project management skills, exhibits your ability to handle challenging projects, brings in critical projects for you, and increases your salary tremendously.

Here are the top 10 benefits of achieving this valuable Credential:

1. It is globally recognized and accepted credential.
2. It sets you apart from your non-credential peers.
3. Recognizes your project management skills worldwide.
4. Enhances your project management skills.
5. Empowers you with skills to Improve project performance.
6. Validates and displays your skills and experience in successfully completing challenging and critical industry-based projects.
7. Increases your value as a PMP and gives you the scope to lead, direct, and implement challenging projects.
8. Provides you greater job opportunities in the global project management scenario.
9. Attaining PMI credential expands your market reach by getting out to potential employers from across the globe.
10. Increases your salary noticeably.

Earn a PMI credential now and step ahead in your Project Management Career

I hope the above-given facts and information helps you to understand the benefits of passing PMI’s certification exam!! If you are looking for this valuable credential then, you should go for it as it can literally change your life. Earning a PMI’s certification confidently, you must be convinced and confident about the Excellency of your study resource and material.

PMIexam.net is giving you a full confidence and encourages your step toward a PMI certification by facilitating you with best study material. Our braindumps are most up-to-date and proven by qualified experts. They are available in PDF file format and Online Exam Engine format also. PDF dumps have a wide range of exam questions to cover the whole course contents of certification exam. Your brilliant success is 100% guaranteed by preparing these exam dumps.

PMI-RMP Braindumps | Your organization has named you… 0

Questions: 8

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

A. Project risks will increase.
B. The project will take longer to complete, but risks will diminish.
C. Project costs will increase.
D. The amount of hours a resource can be used will diminish.

Answer: C

PMP Practice Test | Sammy is the project manager for… 0

Questions : 49

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

A. Harry is correct, because the risk probability and impact considers all objectives of the project.
B. Harry iscorrect, the risk probability and impact matrix is the only approach to risk assessment.
C. Sammy is correct, because organizations can create risk scores for each objective of the project.
D. Sammy is correct, because she is the project manager.

Answer: C

PMI-RMP Dumps | Kelly is the project manager… 0

Questions : 7

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

A. Risk register
B. Risk register updates
C. Change requests
D. Project document updates

Answer: A

PMI-SP Exam Dumps | You are the project manager… 0

Questions : 37

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

A. It is derived from the constraints of the project.
B. It is assigned to the project by management.
C. It is created by the stakeholders.
D. It is developed from the schedule network analysis.

Answer: D

PgMP Practice Exam | A new program is being… 0

Questions : 37

A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

A. Program risk
B. Program benefits
C. Program scope
D. Link to organizational strategy

Answer: A

PMI-RMP Braindumps | You are working with Anna… 0

Question: 5

You are working with Anna on your project to determine and map the probability distributions of risk within the project. You have indicated that you will use the uniform distribution method for a portion of the project. Which part of your project is most likely to have a uniform risk distribution?

A. Late completion stages of a project
B. Project phases that deal with “cutover” technologies
C. Early concept stage of design
D. Project initiating

Answer: C