Question: 47

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A. Supportive
B. Leading
C. Neutral
D. Resistant

Answer: B