We are proud to offer the best quality PMP Dumps to help individuals in getting their desired Project Management certification. PMP braindumps are persistently being revised and updated for relevance and accuracy. You can rely on PMI PMP PDF and PMP Real Exam Questions for the preparation of your actual exam. We 100% guarantee the quality and reliability of this study material; it will lead you to a brilliant success in your certification exam. For your mental satisfaction, you can test our Free PMI PMP Study Material and Free PMP Question Answers before purchase.


Prepare these PMP dumps and pass your exam. PMP test questions answers are collected from real paper. Keep visiting for PMP practice test or PMP braindumps.

Topic: PMP Dumps

PMP Study Material

PMP | Quantitative risk analysis should be performed… 0

Question: 31

Quantitative risk analysis should be performed:

A. only on risks identified by the project manager
B. only in extreme cases
C. only on prioritized risks
D. on all risks

Answer: C

Explanation

C – Since the quantitative risk analysis is a more in-depth process, it should only be performed on prioritized risks to minimize impact to the overall project schedule. [ PMBOK 5th edition , Page 334] [Project Risk Management] Total Total

PMP | The zero duration of milestones in project planning… 0

Question: 30

The zero duration of milestones in project planning occurs because milestones:

A. Are unpredictable and challenge the Plan Schedule Management process.
B. Occur at random times in the project plans.
C. Represent a moment in time such as a significant project point or event.
D. Represent both significant and insignificant points in the project and are difficult to anticipate.

Answer: C